Problem Statement:
The time to complete a complaint investigation needs to be shortened to
accommodate for the frequency of complaints throughout the year to ensure
timelines are met.
Moving onto the improve phase of this project, I utilized
the following tools:
·
Brainstorming
·
Risk v benefit chart
·
ID Alternative Solutions
·
Determine optimal solutions
·
Update FMEA
·
Value Stream mapping(future state)
·
Validate improvements
For the purposes of this blog, I will focus on the use of
the brainstorming, risk v benefit chart, ID alternative solutions, determining
optimal solutions and validate improvements.
Following on from the brainstorming session in the measure
phase, the team met again to review the possible solutions highlighted at the
time and reviewed to determine if there were any other solutions which may be
viable for consideration. During this session, the cause and effect diagram was
also reviewed again to ensure that all problem areas were considered for possible
improvement.
A risk versus benefit chart was utilized for each of the
headings highlighted within the brainstorming session. Solutions from the
brainstorming sessions and any appropriate solutions from the cause and effect
diagram were also slotted in accordingly under each of the headings:
investigation write up, risk, software and additional tasks during this
session. Out of a possible 33 possible solutions, the review yielded the
following results: Implement: 11, Possible: 9, Challenge: 2, Kill: 11.
On review, it was determined that the implementation of the
challenge solutions would not be implemented within the timeframe of the
project and would be added to the list for future improvements.
The necessary actions required to implement the solutions
agreed included various quality system instruction updates, development of
access database and retraining on practices and procedural updates with
investigators and quality engineers.
For example, some of the implement solutions have seen the
following time savings:
·
Remove requirement to view work order, do not
attach the work order.
o
QSI1426 (Complaint Investigations) updated to
remove the requirement to attach the work orders linked to the complaint. Work
orders are in excess of 10MB which required to download, then import to Adobe X
standard to reduce the size of the file and then attach to Trackwise. Time
saved: 18 minutes
·
Do not attach the review of JBASE (manufacturing
operations system).
o
QSI1426 (Complaint Investigations) updated to
remove the requirement to attach the screen shots of JBASE. There were 5 menus
to be reviewed within JBASE to pull the necessary information required. A print
screen was taken of each menu reviewed, cropped and formatted into word and
attached to Trackwise. Time saved: 10 minutes.
·
Limit the level of review, remove requirement to
attach.
o
QSI1426 (Complaint Investigations) updated to
remove the requirement to attach the documents reviewed. The following
documents were downloaded and re-attached to Trackwise for each complaint:
production, final quality control, packaging instructions and the IFUs. In most
cases the IFU as well as some production instructions were also larger than a
10MB file and therefore had to be downloaded, then import to Adobe X standard
to reduce the size of the file and then attach to Trackwise. Time saved: 27 minutes
The implementation of the solutions listed within the
implement and possible buckets of the risk versus benefit charts have resulted
in measureable improvements and therefore it is possible to move onto the final
phase of this project, the control phase.
Assessment of the
Improve Phase: The risk versus benefit charts were very beneficial for
pulling all the possible solutions from the tools used to date and determine
what was worth the effort for implementation. All solutions were viable and
agreed at the time however when it comes to the implementation the risk can
often outweigh the benefit unless it is reviewed beforehand. With the successful
implementation of the solutions, we are already seeing the benefit of our
choices which validates the improvements made and makes to possible to move
onto the final phase of this project.
Next Step:
Control. Maintain the solution.